News Archive by Months
December 2009
QUALIFICATION OF NDT INSPECTION FOR LOVIISA NPP
In-service inspection of reactor pressure vessel and control rod protection pipe welds in Loviisa 1 and 2 in 2010 and 2012 will be performed by previously qualified inspection equipment, NDT procedures and personnel as proposed by Finnish Regulation and Nuclear Safety Authority STUK. INETEC will perform the qualification of the inspection technique and examiners according to Finnish requirements and regulations which are based on the ENIQ recommendations. More...
October 2009
INETEC TO PERFROM ISI OF CONTROL ROD PROTECTION PIPE WELDS AT LOVIISA NPP, FINLAND
INETEC wins a contract for in-service inspection of control rod protection pipe welds in Loviisa 1 and 2 in 2010 and 2012. More...
September 2009
REGIONAL WORKSHOP ON PLANT LIFE MANAGEMENT FOR LONG TERM OPERATION
The Regional Workshop on Plant Life Management for Long Term Operation will take place in Zagreb, INETEC-Institute for Nuclear Technology from November 3 to November 6, 2009. The workshop is within the framework of activities of the IAEA technical cooperation program on Engineering Support for Design, Operation, Maintenance, and Plant Life management for safe long term operation. The purpose of the course is to exchange an experience concerning the integrated plant life management and life extension for WWER NPPs. More...
August 2009
INETEC AWARDED CONTRACT FOR ISI OF REACTOR PRESSURE VESSEL AT LOVIISA NPP, FINLAND
INETEC wins a contract for in-service inspection of reactor pressure vessel in Loviisa 1 and 2 in 2010 and 2012. More...
SUPPLY OF SYSTEM FOR INSIDE INSPECTION OF RPV TO KHMELNITSKY NPP, UKRAINE
INETEC delivers a system for reactor pressure vessel and core barrel metal examination from inside with application of visual, eddy current and ultrasonic technology of phased array to Khmelnitsky NPP, Ukraine. Prior the delivery and in presence of the Purchaser’s representatives, the functional acceptance tests and initial training for the End User’s personnel have been successfully completed. Main training of the End User’s personnel and functional tests are performed in October 2009 at KhNPP site. End of RPV-ISI system qualification and first in-service inspection is scheduled for 2010. More...
June 2009
INSPECTION OF HEAT EXCHANGERS IN CERNAVODA NPP, ROMANIA
INETEC successfully completes inspection of heat exchanger tubes in Cernavoda NPP, Romania. More...
April 2009
RPVH ISI, SG ISI AND ISI SERVICES AT KRSKO NPP, SLOVENIA
INETEC successfully completed reactor pressure vessel head in-service inspection, steam generator in-service inspection and in-service inspection services during the Outage 2009 at Krsko NPP, Slovenia. More...
March 2009
QUALIFICATION OF RPVH REPAIR SERVICE FOR KRSKO NPP
INETEC has developed automatic surface treatment system that provides efficient repair/grinding of the J-groove weld wetted surface. It removes surface abnormalities that can lead to further propagation of the defects. INETEC successfully qualify process of automatic and manual surface indications grinding/polishing on reactor pressure vessel head penetration J-groove weld. More...
February 2009
STEAM GENERATOR INSPECTION AT TIANWAN NPP, CHINA
INETEC provides support to Research Institute of Nuclear Power Operations (RINPO) for eddy current inspection of steam generator tubes at Tianwan NPP, China. More...
|